Garden SIPs Kits

Did you miss our Garden SIPs Kit webpage?

Design Changes

Free of charge up to one round of design changes prior to Stage 2.

From Stage 2 onwards, once drawings have been signed-off and approved, we are unable to make design changes as this will already be in production. The client is to pay in full for the aborted project, and/or a new order will need to be placed, subject to the lead times at that point.

Further changes will be charged at £200 ex VAT per change, including minor and major.

Design Stage (from deposit paid)TimelineApproval Required
Stage one - elevations and floorplan* Week 1 - 2For comment (within 2 days)
Stage two – elevations and floor plan sign-offWeek 2 - 3Adobe E-sign (within 2 days)
Stage three - production drawings for manufacturingWeek 4 - 5None

*  showing the location panel timbers within the SIPs floor (this will inform groundworkers where to install screws or pads)